Oracle Primavera - PM6 As Ronald said Concept of As Ronald said Concept of Baseline Start & FInish, Start & finish dates are different.. I advise you to understand the conecpt of these dates Eckart, When used as a Eckart, When used as a Baseline, the schedule will show Planned Dates, which is sometimes different from Start Dates. Good Luck! Log in or register to post comments
As Ronald said Concept of As Ronald said Concept of Baseline Start & FInish, Start & finish dates are different.. I advise you to understand the conecpt of these dates
Eckart, When used as a Eckart, When used as a Baseline, the schedule will show Planned Dates, which is sometimes different from Start Dates. Good Luck!
As Ronald said Concept of
As Ronald said Concept of Baseline Start & FInish, Start & finish dates are different.. I advise you to understand the conecpt of these dates
Eckart, When used as a
Eckart,
When used as a Baseline, the schedule will show Planned Dates, which is sometimes different from Start Dates. Good Luck!