Multiple Calendar

Member for

16 years 7 months

Ariel,

The predecessor activity finishes at 5pm.

The successor is programmed to start as soon as possible afterwards

You have assigned it a calendar which says it can work from 5pm to 6pm, so that is what it is programming.

 

One method to fix this is to ammend your 10hr calendar so that the 1hr break occurs 5pm - 6pm.

This is only appropriate if you are not interested in the time of day an activity occurs.

Member for

19 years 10 months

Hi Ariel

In PowerProject there is a "Start on Next Day" option.

Look for something similar in P6.

If not you may have to put a 2hr lag on the link.

Best regards

Mike Testro