Printing off Histograms and S-Curves

Member for

15 years 10 months

Sir,

I have a query related to this post. It seems that P6 is showing independently the histograms and curves for budgeted, actual and remaining. What I want is to show that the remaining curve will start at the endpoint of the actual. (remaining is the continuation of the actual) The same as in P3 (Current vs Target 1), the two curves can then show if at the end of the project your actual project cost is higher or lower that the budjeted cost.

Any possible solution?

Thanks in advance.

 

-Marwin-

Member for

16 years 3 months

 
For printing of ur resource histograms and S-curves u hv to go here :
 
1. > view > Show on Bottom > Activity Usage Profile or select whatever u want.
 
after apearing ur profile on bottom follow these steps :
 
2. > File > Print Setup > Options > uncheck all except Profile.
 
i hope it will help u ......
 
 
regards,,,,
 
 
Irfan Khan
 
 

Member for

19 years 2 months

Edward

In print options, deselect activity table and gantt and select profile ..... this should print out the histogram for you. 

Andy