Display all rowsParameterIsValueHigh Value WhereEarly Startis within range ofDDDD+2W OrLate Finishis within range ofDDDD+2W OrActivity StatusequalsIn Progress
concerning schedule update i'm facing problem at cost loaded
after entering the actual percentges for activities i found the cash flow values for baseline changed and i'm sure that i didn't change the dates for baseline
i appeared the baseline separated and checked the values of cash flow i noted that it became true but after assigning the baseline to my updated schedule the cash flow values are changing
plz if help if you can and tell me what is the reason
Thanks for commenting. Yes, your suggestion is certainly helpful especially using the "is within range" term.
I aslo wanted to know if it was necessary to aslo incluse a similar "where" clasue for the Finish date and for activities "in progress". I read on another forum that a look ahead schedule should show:
all things starting within the look ahead period
and finishing within the look ahead period,
as well as all things that are in progress withign the look ahead period.
Do others agree with the above? If meeting all three criteria is the correct protocool would the following filter be suitable?
In Primavera P6 ver. 7 have built in filter of Two Week Look Ached Schedule.
If you want to make in manually so here is the procedure of Two Week Look Ahead Sche.
Go to in Filter > Click New > Give a title of your filer > than chek the perameters like this < Where = Start > in within range of > Value = DD > High Value = DD+2W.
Member for
16 years 3 monthsqyestion was 2 week not 3 or
qyestion was 2 week not 3 or 4
Member for
7 years 6 monthsTo create a look a head
To create a look a head schedule read the articles below
Three Week Look Ahead Schedule in Primavera P6
Four Week Look Ahead Schedule in Primavera P6
Member for
16 years 3 monthsHiahab all you did was copy
Hiahab all you did was copy mine
use the start and fiinsh dates do not use early and late
Display all rows ParameterIs Value HighValue
Where Start is within range of DD DD+2W
Or Finish is within range of DD DD+2W
Or Activity Status equals In Progress
Member for
8 years 5 monthsWhy we are using late Finish
Why we are using late Finish in this below Filter?????
WhereEarly Startis within range ofDDDD+2W OrLate Finishis within range ofDDDD+2W OrActivity StatusequalsIn Progress
In My Opinion below filter is enough.
WhereEarly Startis within range ofDDDD+2W OrActivity StatusequalsIn Progress
Member for
16 years 3 monthsthis shoud do it Display all
this shoud do it
Display all rowsParameterIsValueHigh Value WhereEarly Startis within range ofDDDD+2W OrLate Finishis within range ofDDDD+2W OrActivity StatusequalsIn Progress
Member for
9 years 5 months*
*
Member for
12 years 1 monthHi all , I need to ask how to
Hi all , I need to ask how to make a aevised plan using primavera or recovery plan ?
Member for
12 years 1 monthHi all , I need to ask how to
Hi all , I need to ask how to make a aevised plan using primavera or recovery plan ?
Member for
11 years 11 monthshiiii all concerning
hiiii all
concerning schedule update i'm facing problem at cost loaded
after entering the actual percentges for activities i found the cash flow values for baseline changed and i'm sure that i didn't change the dates for baseline
i appeared the baseline separated and checked the values of cash flow i noted that it became true but after assigning the baseline to my updated schedule the cash flow values are changing
plz if help if you can and tell me what is the reason
thanks
Member for
14 years 8 monthsIrfan, Thanks for
Irfan,
Thanks for commenting. Yes, your suggestion is certainly helpful especially using the "is within range" term.
I aslo wanted to know if it was necessary to aslo incluse a similar "where" clasue for the Finish date and for activities "in progress". I read on another forum that a look ahead schedule should show:
Do others agree with the above? If meeting all three criteria is the correct protocool would the following filter be suitable?
Display all rows
Parameter
Is
Value
High Value
Where
Start
is within range of
DD
DD+2W
Or
Finish
is within range of
DD
DD+2W
Or
Activity Status
equals
In Progress
Thanks all,
Regards,
LP6
Member for
16 years 3 monthsHi, In Primavera P6 ver. 7
Hi,
In Primavera P6 ver. 7 have built in filter of Two Week Look Ached Schedule.
If you want to make in manually so here is the procedure of Two Week Look Ahead Sche.
Go to in Filter > Click New > Give a title of your filer > than chek the perameters like this < Where = Start > in within range of > Value = DD > High Value = DD+2W.
Hope this ill help u.