How to create a 2wk look ahead schedule in P6

Member for

16 years 3 months

Hiahab all you did was copy mine

use the start and fiinsh dates do not use early and late 

Display all rows            ParameterIs               Value                HighValue 

Where               Start is within range of           DD                    DD+2W 

Or                     Finish is within range of         DD                    DD+2W 

Or                Activity Status                           equals                 In Progress

Member for

8 years 5 months

Why we are using late Finish in this below Filter?????

WhereEarly Startis within range ofDDDD+2W  OrLate  Finishis within range ofDDDD+2W  OrActivity StatusequalsIn Progress

 

In My Opinion below filter is enough.

WhereEarly Startis within range ofDDDD+2W        OrActivity StatusequalsIn Progress

Member for

16 years 3 months

this shoud do it 

Display all rowsParameterIsValueHigh Value  WhereEarly Startis within range ofDDDD+2W  OrLate Finishis within range ofDDDD+2W  OrActivity StatusequalsIn Progress

Member for

9 years 5 months

*

Member for

12 years 1 month

Hi all , I need to ask how to make a aevised plan using primavera or recovery plan ?

Member for

12 years 1 month

Hi all , I need to ask how to make a aevised plan using primavera or recovery plan ?

Member for

11 years 11 months

hiiii  all 

  concerning  schedule  update   i'm   facing  problem  at   cost  loaded  

after  entering  the  actual  percentges  for   activities   i  found   the  cash flow  values  for  baseline   changed  and  i'm  sure  that  i  didn't  change  the  dates  for  baseline  

i  appeared  the baseline   separated  and  checked   the  values  of  cash flow   i noted  that it  became  true    but  after  assigning  the baseline   to  my  updated schedule   the   cash flow values   are  changing 

 

 

plz if  help  if  you  can  and  tell  me  what is the reason 

thanks

Member for

14 years 8 months

Irfan,

 Thanks for commenting. Yes, your suggestion is certainly helpful especially using the "is within range" term.

 

I aslo wanted to know if it was necessary to aslo incluse a similar "where" clasue for the Finish date and for activities "in progress". I read on another forum that a look ahead schedule should show:

  • all things starting within the look ahead period
  • and finishing within the look ahead period,
  • as well as all things that are in progress withign the look ahead period.

Do others agree with the above? If  meeting all three criteria is the correct protocool would the following filter be suitable?

 

Display all rows
Parameter
Is
Value
High Value

  Where
Start
is within range of
DD
DD+2W

  Or
Finish
is within range of
DD
DD+2W

  Or
Activity Status
equals
In Progress
  

Thanks all,

Regards,

LP6

Member for

16 years 3 months

Hi,

 

In Primavera P6 ver. 7 have built in filter of Two Week Look Ached Schedule.

If you want to make in manually so here is the procedure of Two Week Look Ahead Sche.

Go to in Filter > Click New > Give a title of your filer > than chek the perameters like this < Where = Start > in within range of > Value = DD > High Value = DD+2W.

 

Hope this ill help u.

 

regards