Level of Effort Percentage complete?

1 reply [Last post]
DAVID SMITH
User offline. Last seen 10 years 37 weeks ago. Offline
Joined: 24 Mar 2004
Posts: 28

Morning,

Have a few level of efforts in my current plan.  Haven't used them for a while and I am a little confused to how  the 'LOE' updates its percentage complete in relation to it's predecessors and successors.

I have one LOE with four activities tied into it, they all have Percentage complete type as 'pyhsical'.  each of these have varying amounts of % comp, but the LOE still remains at 0%.

 % comp can not be hand typed into a LOE, so how does one get this to calculate?

Many thanks in advance

 

Dave

Replies

Raymund de Laza
User offline. Last seen 31 weeks 1 day ago. Offline
Joined: 23 Nov 2009
Posts: 762

Hi Dave,

Physical percentage will not roll up to the summary row. It will just show the physical percentage of individual activity. .

Only Duration % Type will roll up to the summary.

 

This is as per my experience.