Copy a WBS from EPS to Another EPS

Member for

16 years 4 months

Hi

1.Just Select The Two Project you want to open (Ctrl Key).

2. Right Click & Open the Project

3.Now Both Project Are Opened. You can Collapse it to Level 1 (You can see both project Title) .

4.Now Click on WBS Window

5. Just Copy the WBS you Want & Paste the Wbs Where you Want.

Regards

Anbin