Oracle Primavera - PM6 Member for 17 years 6 months Member for 17 years 6 months Submitted by Shazia khan on Thu, 2010-11-11 05:21 Permalink Please check your Please check your calennder it set to 8 hr per day or 10 hr per day. execavation is a construction activity, in general construction activity time is 10 hr per day. (site working time 10 hr per day) and Engineering main office worked 8 hr per day , 5 or 6 days per week first you check calender. ( ste hr / day week, Month , & years) 2nd assign a right cal to activity 3rd check admin preference setting. may it can work for you. Member for 14 years 11 months Member for 14 years 11 months Submitted by Walid Lahiani on Wed, 2010-11-10 11:24 Permalink Thank you ! Why I have to Thank you ! Why I have to choice fixed Unit and not another type (physical,.....) I mean how we choice the type : fixed unit or fixed duration,.... thanks Member for 20 years 1 month Member for 20 years 1 month Submitted by Shareef Abdul Azeez on Wed, 2010-11-10 11:11 Permalink Hi Wahid, In your case, Hi Wahid, In your case, before changing duration to 2 days ,,,set Duration Type: Fixed Units. Then change duration. Best Regards Shareef A Azeez Log in or register to post comments
Member for 17 years 6 months Member for 17 years 6 months Submitted by Shazia khan on Thu, 2010-11-11 05:21 Permalink Please check your Please check your calennder it set to 8 hr per day or 10 hr per day. execavation is a construction activity, in general construction activity time is 10 hr per day. (site working time 10 hr per day) and Engineering main office worked 8 hr per day , 5 or 6 days per week first you check calender. ( ste hr / day week, Month , & years) 2nd assign a right cal to activity 3rd check admin preference setting. may it can work for you.
Member for 14 years 11 months Member for 14 years 11 months Submitted by Walid Lahiani on Wed, 2010-11-10 11:24 Permalink Thank you ! Why I have to Thank you ! Why I have to choice fixed Unit and not another type (physical,.....) I mean how we choice the type : fixed unit or fixed duration,.... thanks
Member for 20 years 1 month Member for 20 years 1 month Submitted by Shareef Abdul Azeez on Wed, 2010-11-10 11:11 Permalink Hi Wahid, In your case, Hi Wahid, In your case, before changing duration to 2 days ,,,set Duration Type: Fixed Units. Then change duration. Best Regards Shareef A Azeez
Member for
17 years 6 monthsPlease check your
Please check your calennder
it set to 8 hr per day or 10 hr per day.
execavation is a construction activity, in general construction activity time is 10 hr per day. (site working time 10 hr per day)
and Engineering main office worked 8 hr per day , 5 or 6 days per week
first you check calender. ( ste hr / day week, Month , & years)
2nd assign a right cal to activity
3rd check admin preference setting.
may it can work for you.
Member for
14 years 11 monthsThank you ! Why I have to
Thank you !
Why I have to choice fixed Unit and not another type (physical,.....)
I mean how we choice the type : fixed unit or fixed duration,....
thanks
Member for
20 years 1 monthHi Wahid, In your case,
Hi Wahid,
In your case, before changing duration to 2 days ,,,set Duration Type: Fixed Units.
Then change duration.
Best Regards
Shareef A Azeez