When I make down the original duration , the ressource allocation became overloaded but the unit/TIME didn't change

Member for

17 years 6 months

Please check your calennder

 

it set to 8 hr per day or 10 hr per day.

 execavation is a construction activity, in general construction activity  time is 10 hr per day. (site working time 10 hr per day)

 

and Engineering main office  worked 8 hr per day , 5 or 6 days per week

 

first you check calender. ( ste hr / day  week, Month , & years)

2nd assign a right cal to activity

3rd check admin preference setting.

may it can work for you.

Member for

14 years 11 months

Thank you !

 

Why I have to choice fixed Unit and not another type (physical,.....)

I mean how we choice the type : fixed unit or fixed duration,....

thanks

Member for

20 years 1 month

Hi Wahid,

 

In your case, before changing duration to 2 days ,,,set Duration Type: Fixed Units.

Then change duration.

 

Best Regards

Shareef A Azeez