Global Activity Code does not appear in Group/Sort

2 replies [Last post]
Peter Clapp
User offline. Last seen 7 years 30 weeks ago. Offline
Joined: 21 Nov 2008
Posts: 11
Groups: None

The contractor exports (using P3e v.5) EPS level Activity Codes as Globals; We import, using P6.2.1, as .XER (code values to be updated) and although the Activity Code is in the dictionary and the assigned values are present (against each activity) the Code cannot be seen in the Group/Sort function. If the code is re-named, it appears. Any ideas?

Replies

Peter Clapp
User offline. Last seen 7 years 30 weeks ago. Offline
Joined: 21 Nov 2008
Posts: 11
Groups: None

Thanks for your reply Mike. You're right, but in this instance all codes are Global, there are no EPS or Project codes. I've also checked the Import Configuration, which is set to 'update existing' Activity Codes. A poster on the Primavera forum suggested this is a known bug in P6. Have any other P6 users experienced this?

Mike Peyton
User offline. Last seen 9 years 49 weeks ago. Offline
Joined: 28 Oct 2010
Posts: 3
Groups: None

Peter,

I've seen this before, but only when an activity code (whether it is project, EPS or global) has been duplicated. If you have the same code defined at one of the other levels then this will cause that; the key is when you said that you renamed it then it appeared.