I donot think this is a fault in P6 coz when you look at it a start milestone doesnot have any duration. It looks as though u r wasting a day saying your project has started.
Anyways have you tried scheduling with ur data date set at the last working hour of the day.....for eg DD:15/9/10 18:00(or the last hour set in ur calendar)
1d lag is a remedy, but that is not the correct way to do this. Especially when you have many start milestones in the schedule i.e. recv material, recv Dwgs, NTP, Contract Award. All of these examples would be most likely followed by a task dependent activity. I've seen this issue before in P5/P6 and thought It had been resolved, but the steps was told to use are not working anymore.
Any other suggestions?
Member for
15 years 8 months
Member for15 years8 months
Submitted by Satish Kumar on Wed, 2010-09-22 18:58
Member for
16 years 8 monthsTime Period
Hi
Due to the working hours equal 10 hours a day, you should change `default 8 hour a day` to `10 hour a day`.
Admin> Admin Preferences>Time Periods tabs and change the working hours daily, weekly and monthly
And also change working times in your calender, `default 8 hour a day` to `10 hour a day`
Enterprise>Calender>`Choose your calender` Modify>Workweek
Take care
Member for
20 years 1 monthok, I didn't see ur second
ok,
I didn't see ur second post where you said u have many milestones.
In this case what Satish mentioned would be the best thing to do.
Best Regards
Shareef A Azeez
Member for
20 years 1 monthHi Lopez I donot think this
Hi Lopez
I donot think this is a fault in P6 coz when you look at it a start milestone doesnot have any duration. It looks as though u r wasting a day saying your project has started.
Anyways have you tried scheduling with ur data date set at the last working hour of the day.....for eg DD:15/9/10 18:00(or the last hour set in ur calendar)
Best Regards
Shareef A Azeez
Member for
15 years 1 month1d lag is a remedy, but that
1d lag is a remedy, but that is not the correct way to do this. Especially when you have many start milestones in the schedule i.e. recv material, recv Dwgs, NTP, Contract Award. All of these examples would be most likely followed by a task dependent activity. I've seen this issue before in P5/P6 and thought It had been resolved, but the steps was told to use are not working anymore.
Any other suggestions?
Member for
15 years 8 monthsFS+1
HI Lopegr,
ur milestone has 0 duration? can't u give a lag of 1 day?
Regards
K