Start Milestone FS Task Dependent Activity (Date problem)

Member for

16 years 8 months

Hi

Due to the working hours equal  10 hours a day, you should  change `default 8 hour a day` to `10 hour a day`.

Admin> Admin Preferences>Time Periods tabs and change the working hours daily, weekly and monthly

And also change working times in your calender, `default 8 hour a day` to `10 hour a day`

Enterprise>Calender>`Choose your calender` Modify>Workweek

 

Take care

Member for

20 years 1 month

ok,

I didn't see ur second post where you said u have many milestones.
In this case what Satish mentioned would be the best thing to do.

Best Regards
Shareef A Azeez

Member for

20 years 1 month

Hi Lopez

I donot think this is a fault in P6 coz when you look at it a start milestone doesnot have any duration. It looks as though u r wasting a day saying your project has started.

Anyways have you tried scheduling with ur data date set at the last working hour of the day.....for eg DD:15/9/10 18:00(or the last hour set in ur calendar)

Best Regards
Shareef A Azeez

Member for

15 years 1 month

1d lag is a remedy, but that is not the correct way to do this.  Especially when you have many start milestones in the schedule i.e. recv material, recv Dwgs, NTP, Contract Award.  All of these examples would be most likely followed by a task dependent activity.  I've seen this issue before in P5/P6 and thought It had been resolved, but the steps was told to use are not working anymore. 

Any other suggestions?

Member for

15 years 8 months

HI Lopegr,

ur milestone has 0 duration? can't u give a lag of 1 day? 

 

Regards

K