Go to report wizard, select “Activity Resource and Role Assignment” as the subject. Select Activity ID and Resource ID for the columns and the ‘Remaining units’ under the timescale data tab. Take out criteria under the Group and Sort and print the output in CSV, everything will be in there.
RE: Reporting Resource Budgeted Hours
Go to report wizard, select “Activity Resource and Role Assignment” as the subject. Select Activity ID and Resource ID for the columns and the ‘Remaining units’ under the timescale data tab. Take out criteria under the Group and Sort and print the output in CSV, everything will be in there.