Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

PLANNED PERCENTAGE

4 replies [Last post]
kumar s
User offline. Last seen 9 years 24 weeks ago. Offline
Joined: 26 Jan 2010
Posts: 159
Dear ALL,

what is the best method to know the planned percentage of work per day in advance .
how to calculate it.
is it with respect to the hrs of resources used per day to the total hrs of resources required for the whole project .



Replies

Izam Zakaria
User offline. Last seen 8 years 27 weeks ago. Offline
Joined: 28 May 2006
Posts: 221

Kumar,

U never produce S-Curve(xls) from P6 before? it is the same method right? but u have to select the option "Tabulated by days" from there u can get your tabulation by daily.

If i did expalin this wrongly, guys u are pleased to correct me.
Francis Moyalan, ...
User offline. Last seen 6 years 4 weeks ago. Offline
Joined: 12 Feb 2005
Posts: 105
Groups: None
Hi Kumar,

Option-1
one way of doing this is to assign a resource which is ’upt’which shall take the duration of every activity as the budgeted quantity which will help you in arriving at a planned percentage on exporting the budgeted values per month to excel or you can go for the resource profile month wise to get the palnned percenatge.

Option-2
other way is to assign resources - labour.material and plant/ equipment which will be the more accurate way of doing it but....as you know it is an uphill task .

may be option 1 willl help u in this case.

cheers
Joel Gilbert
User offline. Last seen 5 years 34 weeks ago. Offline
Joined: 5 May 2003
Posts: 166
Copy your schedule in excel and do it there it is much easier
Rola Sabbah
User offline. Last seen 11 years 33 weeks ago. Offline
Joined: 5 Dec 2009
Posts: 61
hi kumar,
what i do is to save another copy of the program and then use apply actual function and you will see the planned precentage and then compare it to the actual.
and if you want in advance you can put the data date in the next day date and then subtracting the previous percentage, but i think it will be time consuming