Recurring Holidays

Member for

15 years 4 months
Permalink

Thanks, Rodel. That’s kind of what I thought but it gets to be a bit tedious going through each month especially if it’s a multiyear project. It may be a small thing but I always wonder why they would take away some of the P3 functions that were helpful.

I will use the Global Inherit feature for sure.

Member for

19 years
Permalink

Kari,
In P6 you have to define it every year but once you define a global calendar with holiday and exemption you can insert those periods for any created resource & project calendar by selecting global calendar into "Inherit holiday and exemptions from Global Calendar". You will notice a global icon will be inserted to resource or project calendar once selected.