Thanks, Rodel. Thats kind of what I thought but it gets to be a bit tedious going through each month especially if its a multiyear project. It may be a small thing but I always wonder why they would take away some of the P3 functions that were helpful.
Kari,
In P6 you have to define it every year but once you define a global calendar with holiday and exemption you can insert those periods for any created resource & project calendar by selecting global calendar into "Inherit holiday and exemptions from Global Calendar". You will notice a global icon will be inserted to resource or project calendar once selected.
RE: Recurring Holidays
Thanks, Rodel. Thats kind of what I thought but it gets to be a bit tedious going through each month especially if its a multiyear project. It may be a small thing but I always wonder why they would take away some of the P3 functions that were helpful.
I will use the Global Inherit feature for sure.
RE: Recurring Holidays
Kari,
In P6 you have to define it every year but once you define a global calendar with holiday and exemption you can insert those periods for any created resource & project calendar by selecting global calendar into "Inherit holiday and exemptions from Global Calendar". You will notice a global icon will be inserted to resource or project calendar once selected.