Level Resources automatically getting ticked

1 reply [Last post]
Haresh Jayanth
User offline. Last seen 6 years 11 weeks ago. Offline
Joined: 24 Aug 2006
Posts: 219
Hi Rodel,

Before importing a program , i untick the option in Tool , Level resources , "Level all resources".

But when i import a program back , this option "Level all resources" is getting activated again"......

Even when i am importing i have removed "Keep existing option for all the parameters to "Update existing" still i am not able to remove this option..

Kindly advice....

regards,

Haresh Jayanth

Replies

Rodel Marasigan
User offline. Last seen 2 days 3 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Haresh,
Scheduling Options and level options settings are exported in XER under SCHEDOPTION table and it will keep the settings option if your import action is to update the existing database or Project. If your import action is Create New Project then all settings will goes back to default like level all resources and preserve scheduled early and late dates etc…