Oracle Primavera - PM6 Member for 19 years Member for 19 years Submitted by Rodel Marasigan on Tue, 2010-05-25 03:51 Permalink RE: Confusion between budget.... Irfan, Original Budget is Contract Amount including Overhead, Provisional Sum, Profit, Margin etc... Budget At Completion (BAC) = Budget + Approved Variation/Changes use as base to measure Earned Value. AT Completion = Actual cost + Remaining cost = Forecast At Completion Log in or register to post comments
Member for 19 years Member for 19 years Submitted by Rodel Marasigan on Tue, 2010-05-25 03:51 Permalink RE: Confusion between budget.... Irfan, Original Budget is Contract Amount including Overhead, Provisional Sum, Profit, Margin etc... Budget At Completion (BAC) = Budget + Approved Variation/Changes use as base to measure Earned Value. AT Completion = Actual cost + Remaining cost = Forecast At Completion
Member for
19 yearsRE: Confusion between budget....
Irfan,
Original Budget is Contract Amount including Overhead, Provisional Sum, Profit, Margin etc...
Budget At Completion (BAC) = Budget + Approved Variation/Changes use as base to measure Earned Value.
AT Completion = Actual cost + Remaining cost = Forecast At Completion