Oracle Primavera - PM6 Member for 19 years Member for 19 years Submitted by Rodel Marasigan on Sun, 2010-05-23 08:29 Permalink RE: How to send a copy as target baseline Haresh, You need to detach the baseline and restore then export together with current project and will create only one xer then if emailed to someone inform the recipient to attach the baseline after importing. Log in or register to post comments
Member for 19 years Member for 19 years Submitted by Rodel Marasigan on Sun, 2010-05-23 08:29 Permalink RE: How to send a copy as target baseline Haresh, You need to detach the baseline and restore then export together with current project and will create only one xer then if emailed to someone inform the recipient to attach the baseline after importing.
Member for
19 yearsRE: How to send a copy as target baseline
Haresh,
You need to detach the baseline and restore then export together with current project and will create only one xer then if emailed to someone inform the recipient to attach the baseline after importing.