How to add Budgeted Units directly using Global change

1 reply [Last post]
Haresh Jayanth
User offline. Last seen 6 years 8 weeks ago. Offline
Joined: 24 Aug 2006
Posts: 219
Hi

I want to add for all concreting activities same Budget units for eg 240.......using global change.....as we used to do in P3.1

So in if statement i selected activity name..Concreting.....

But when we come to then statement..in P6.1 , we have to add two parameters, how to use these parameters to add my budgeted units = 240 for all concreting activities.....

can anyone guide me..
regards,

Haresh Jayanth

Replies

Rodel Marasigan
User offline. Last seen 8 hours 59 min ago. Offline
Joined: 25 Oct 2006
Posts: 1699
See sample below:
Global Change