Activities when imported moves out of WBS

2 replies [Last post]
Salman Ahmed
User offline. Last seen 13 years 46 weeks ago. Offline
Joined: 2 Mar 2010
Posts: 54
Hi all,

Request your suggestions on the following situation:

I exported the activities for weightage calculations.When these activites are imported back to P6, they moved from their original WBS to Project level WBS.





Replies

Salman Ahmed
User offline. Last seen 13 years 46 weeks ago. Offline
Joined: 2 Mar 2010
Posts: 54
Thank you Mr.Rodel for your support.

Salman
Rodel Marasigan
User offline. Last seen 20 hours 3 min ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Salman,

When exporting files from Primavera, don’t delete the WBS Code column, this is one of the basic unique identifier of activity. If this column remove and import back, all activities will move to Project level WBS and delete the current assignment.