Planned progress = Schedule % complete in Primavera. If you want to display the %complete on bar then click the Bar icon. Tick the baseline you want to show (Project BL, Primary BL...etc) While highlighted the selected baseline click the bar level tab. Click add and select where you want it to be display (i.e. Right, Left, Center..etc) then Select Schedule % Complete. Do the same on Actual Bar and select Activity % Complete.
Member for
19 yearsRE: Comparison between Baseline & Actual
Planned progress = Schedule % complete in Primavera. If you want to display the %complete on bar then click the Bar icon. Tick the baseline you want to show (Project BL, Primary BL...etc) While highlighted the selected baseline click the bar level tab. Click add and select where you want it to be display (i.e. Right, Left, Center..etc) then Select Schedule % Complete. Do the same on Actual Bar and select Activity % Complete.
This should display the % Complete on each bar