summarize data

2 replies [Last post]
Gerrit Bruns
User offline. Last seen 11 years 44 weeks ago. Offline
Joined: 26 Feb 2010
Posts: 4
Hy everybody,

can someone explain how tools> "summarize" works (or what its good for), how this is related to the "settings" tab in the project details and where I can finally see the effects. I still couldnt find the reasonable usage for this function.

thanks in advance,
Gerrit

Replies

Gerrit Bruns
User offline. Last seen 11 years 44 weeks ago. Offline
Joined: 26 Feb 2010
Posts: 4
thanks a lot for your support.

greetings,
Gerrit
Ian Nicholson
User offline. Last seen 14 years 2 weeks ago. Offline
Joined: 29 Jan 2010
Posts: 42
Summarize Data allows you to see data about closed projects. If you look in the projects window, for a field like At Completion Total Cost, you will see a different result when the project is open or closed.

Summarizing a project stores a number of project (and WBS)level fields with live data from the project. Once summarization is complete, the two values are aligned.

This is so that cross project rollups can be done without opening all the projects in the database at the same time. It is also useful when you want to publish information periodically (such as after a schedule update).