Baseline Schedule disappeared after importing process

Member for

11 years 3 months

hello guys , it's  mega , just done with my p6 programme and was  given this link by my instructor , i know being in  here .. i am gonna learn swiftly.

cheers

Member for

16 years 6 months

You are right Dieter. I did not notice that the baseline copying option was unticked after I re-installed P6 last week. Thanks for highlighting. God Bless.



Cheers,



Jaya

Member for

18 years 9 months

Jaya



Maybe your mistake was during copy.



When you copy a project with bl assigned, you can mark if bl to be copied as well. Then another window opens showing the bl and you can mark which one(s) to be copied with the project. This bl you can assign to your copied project. If it was assigned, the copied bl will be assigned to the copied project.



When you show the bl of your copied project (Project --> Maintain BL) what is displayd?



Regards



Dieter

Member for

16 years 6 months

Dear guys,



I have another question related to the baseline.



I have recently made a copy of a schedule which has a baseline assigned and the progress updated. When i open the copy of the schedule, the baseline is missing but the BL1 Start and BL1 Finish is showing the baseline dates. It appears to that the baseline schedule has been embedded to the copies schedule. Now my problem is i cant remove the baseline schedule or update with a new one. Assist me please.



I need to remove the baseline and assign a new revised baseline.