You are right Dieter. I did not notice that the baseline copying option was unticked after I re-installed P6 last week. Thanks for highlighting. God Bless.
Cheers,
Jaya
Member for
18 years 9 months
Member for18 years9 months
Submitted by Dieter Wambach on Tue, 2009-12-15 01:57
When you copy a project with bl assigned, you can mark if bl to be copied as well. Then another window opens showing the bl and you can mark which one(s) to be copied with the project. This bl you can assign to your copied project. If it was assigned, the copied bl will be assigned to the copied project.
When you show the bl of your copied project (Project --> Maintain BL) what is displayd?
Regards
Dieter
Member for
16 years 6 months
Member for16 years6 months
Submitted by Ir. P. Jaya Chandar on Tue, 2009-12-15 00:21
I have recently made a copy of a schedule which has a baseline assigned and the progress updated. When i open the copy of the schedule, the baseline is missing but the BL1 Start and BL1 Finish is showing the baseline dates. It appears to that the baseline schedule has been embedded to the copies schedule. Now my problem is i cant remove the baseline schedule or update with a new one. Assist me please.
I need to remove the baseline and assign a new revised baseline.
Member for
18 years 9 months
Member for18 years9 months
Submitted by Dieter Wambach on Thu, 2009-12-10 08:18
Member for
11 years 3 monthshello guys , it's mega ,
hello guys , it's mega , just done with my p6 programme and was given this link by my instructor , i know being in here .. i am gonna learn swiftly.
cheers
Member for
16 years 6 monthsRE: Baseline Schedule disappeared after importing process
You are right Dieter. I did not notice that the baseline copying option was unticked after I re-installed P6 last week. Thanks for highlighting. God Bless.
Cheers,
Jaya
Member for
18 years 9 monthsRE: Baseline Schedule disappeared after importing process
Amendment
If no bl is assigned, e.g. under BL Start Date the Planned Start Date is shown.
Dieter
Member for
18 years 9 monthsRE: Baseline Schedule disappeared after importing process
Jaya
Maybe your mistake was during copy.
When you copy a project with bl assigned, you can mark if bl to be copied as well. Then another window opens showing the bl and you can mark which one(s) to be copied with the project. This bl you can assign to your copied project. If it was assigned, the copied bl will be assigned to the copied project.
When you show the bl of your copied project (Project --> Maintain BL) what is displayd?
Regards
Dieter
Member for
16 years 6 monthsRE: Baseline Schedule disappeared after importing process
Dear guys,
I have another question related to the baseline.
I have recently made a copy of a schedule which has a baseline assigned and the progress updated. When i open the copy of the schedule, the baseline is missing but the BL1 Start and BL1 Finish is showing the baseline dates. It appears to that the baseline schedule has been embedded to the copies schedule. Now my problem is i cant remove the baseline schedule or update with a new one. Assist me please.
I need to remove the baseline and assign a new revised baseline.
Member for
18 years 9 monthsRE: Baseline Schedule disappeared after importing process
Youre welcome
Member for
19 years 5 monthsRE: Baseline Schedule disappeared after importing process
Hi Friend,
You always there for me. Thank you so much buddy.
Cheers
Member for
18 years 9 monthsRE: Baseline Schedule disappeared after importing process
Izam
Youre right, export doesnt include the baseline; only copy does.
Regards
Dieter