We need to under stand from you what you mean by "Budget Quantity"?
The most likely explanation is that it is the tender quantity for each line item.
The Quantities are estimated quantities that are calculated by quantity surveyors at the tender stage. It is a standard process where the tenders are reviewed and quantities are calculated depending on the Tender Documents, details, and specifications.
With kind regards,
Samer
Member for
20 years 2 months
Member for20 years2 months
Submitted by Milind Pandhare on Wed, 2009-09-30 16:26
Member for
17 years 2 monthsRE: How to Calculate Budget Quantity ?
Dear Irfan,
We need to under stand from you what you mean by "Budget Quantity"?
The most likely explanation is that it is the tender quantity for each line item.
The Quantities are estimated quantities that are calculated by quantity surveyors at the tender stage. It is a standard process where the tenders are reviewed and quantities are calculated depending on the Tender Documents, details, and specifications.
With kind regards,
Samer
Member for
20 years 2 monthsRE: How to Calculate Budget Quantity ?
Irfan
there is no Budgeted Quantity as such in P6
if you want to load Quantity as resource
Make a resource (Resource type =Material)
Asign unit for that resource (Chq Admin preferance for units)
and for a perticular activity asign that Resource with Budgeted unit =What u want
it will be the quantity for ur use
Milind
Member for
18 years 6 monthsRE: How to Calculate Budget Quantity ?
Hi Irfan,
I presumed you are working with Road Works. You mean "Cut & Fill" for Earthworks?
Regards.
Member for
19 years 1 monthRE: How to Calculate Budget Quantity ?
cutting in cubic meters? I supposed you are going to cut concrete, is it a demolition work?
I believe you had already mentioned the budget quantity and that is in terms of m3. Or do you mean another thing?