P6 Updating progress via excel file

3 replies [Last post]
Izam Zakaria
User offline. Last seen 8 years 23 weeks ago. Offline
Joined: 28 May 2006
Posts: 221
I’ve been export the P6 input into excel such like (physical % complete, Actual Start / Finish & remaining duration but the problem is physical % complete have this signal (*). Is it I still have any option to fix this problem?

Replies

MOKHZANI MOHSIN
User offline. Last seen 14 years 12 weeks ago. Offline
Joined: 17 Sep 2005
Posts: 3
Groups: GPC Malaysia

create one user define - export to excel > update in excel > import to p6 > global change

James bid
User offline. Last seen 10 years 35 weeks ago. Offline
Joined: 8 Oct 2009
Posts: 50

Good Day Arnold!

I experienced the same problem as Izam, It is very beneficial to us if you can provide us steps to do these. Or screenshots may be helpful as well.

chris.pambid1980@yahoo.com

 

Thank you so much

chris

Arnold Puy
User offline. Last seen 10 years 15 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Izam,

You can fix this problem by using the PATTLNK_632006_536-xerFileParser&Builder.

Regards,

Arnold