Oracle Primavera - PM6 Member for 16 years 11 months Member for 16 years 11 months Submitted by Ruel Camaquin on Thu, 2009-07-16 22:27 Permalink RE: breaking schudule bar into 2 bar Oliver, Thanks for that. Cheers! Member for 18 years 6 months Member for 18 years 6 months Submitted by Oliver Melling on Thu, 2009-07-16 05:14 Permalink RE: breaking schudule bar into 2 bar Ruel, You cannot split tasks in P6 when planning, as far as i know. You will need to put in multiple tasks. The only scenario where you can split a task is during updating progress, when the suspend and resume function can be used. Log in or register to post comments
Member for 16 years 11 months Member for 16 years 11 months Submitted by Ruel Camaquin on Thu, 2009-07-16 22:27 Permalink RE: breaking schudule bar into 2 bar Oliver, Thanks for that. Cheers!
Member for 18 years 6 months Member for 18 years 6 months Submitted by Oliver Melling on Thu, 2009-07-16 05:14 Permalink RE: breaking schudule bar into 2 bar Ruel, You cannot split tasks in P6 when planning, as far as i know. You will need to put in multiple tasks. The only scenario where you can split a task is during updating progress, when the suspend and resume function can be used.
Member for
16 years 11 monthsRE: breaking schudule bar into 2 bar
Oliver,
Thanks for that.
Cheers!
Member for
18 years 6 monthsRE: breaking schudule bar into 2 bar
Ruel,
You cannot split tasks in P6 when planning, as far as i know.
You will need to put in multiple tasks.
The only scenario where you can split a task is during updating progress, when the suspend and resume function can be used.