Relationship lines

Member for

19 years 6 months
Permalink

Thank you all

Just worked out!!!!!!!
That was fantastic.

Keep it up.

Julius Achy

Member for

24 years 6 months
Permalink

Move the Baseline bar below the other bars in the bars form and this will put the relationships on the current schedule bars.

Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers, Consulting and Training
<a href="http://www.eh.com.au/">www.eh.com.au</a&gt;

Member for

20 years 3 months
Permalink

Hi Julius

this is caused by the sequence of the bars in the Bar-format window. Just put yr current bar up, so it is before yr baseline bar