Move the Baseline bar below the other bars in the bars form and this will put the relationships on the current schedule bars.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers, Consulting and Training
<a href="http://www.eh.com.au/">www.eh.com.au</a>
RE: Relationship lines
Thank you all
Just worked out!!!!!!!
That was fantastic.
Keep it up.
Julius Achy
RE: Relationship lines
Move the Baseline bar below the other bars in the bars form and this will put the relationships on the current schedule bars.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers, Consulting and Training
<a href="http://www.eh.com.au/">www.eh.com.au</a>
RE: Relationship lines
Hi Julius
this is caused by the sequence of the bars in the Bar-format window. Just put yr current bar up, so it is before yr baseline bar