Peak Manpower in the Resource Histogram

12 replies [Last post]
Glenn Dexter Ubaldo
User offline. Last seen 11 years 29 weeks ago. Offline
Joined: 17 Jun 2009
Posts: 23
Hello everyone,

I would like to ask if anyone could explain to me how to show the Peak manpower either on report or by histogram in
P6 because I use this option often in P3 but know our current project requires us to use P6 but I cannot locate this option. I would very much appreciate if any one could help me.

Glenn,

Replies

A.Jaffer Sadiq
User offline. Last seen 5 years 25 weeks ago. Offline
Joined: 16 Oct 2008
Posts: 33
Groups: GPC Qatar

Can you please send a copy at jafferplanner@gmail.com

Thanks in advance

Neal Walsh
User offline. Last seen 3 years 28 weeks ago. Offline
Joined: 16 Sep 2007
Posts: 49
Hi Eric,

Could you please also send me a copy?

waltav@hotmail.com

thanks very much.....

Walshy
Mohammed Amjad Gh...
User offline. Last seen 10 years 23 weeks ago. Offline
Joined: 2 Sep 2006
Posts: 5
Groups: None
Hello Eric,

Please send me a copy also at amjad.ghaniwala@gmail.com.

Thanks,
Amjad
Jojie Pepito
User offline. Last seen 5 years 33 weeks ago. Offline
Joined: 12 Oct 2009
Posts: 15
Can you [lease send a copy at jpepito78@yahoo.com

thanks!

jojie
Artur Correa
User offline. Last seen 15 years 4 weeks ago. Offline
Joined: 14 Nov 2007
Posts: 5
Groups: None
Hello Eric,

Can you please also send a copy at correa1980@gmail.com

Thank you in advance
Artur
kalpesh dalvi
User offline. Last seen 14 years 43 weeks ago. Offline
Joined: 11 Jun 2009
Posts: 7
Can you please send a copy at Kalpesh.Dalvi@kcm.co.zm.

Thanks in advance
R. Catalan
User offline. Last seen 12 years 8 weeks ago. Offline
Joined: 15 Aug 2005
Posts: 314
Groups: None
Eric,

Pls send me a copy to planning_me@yahoo.com

Thanks,
R. Catalan
Glenn Dexter Ubaldo
User offline. Last seen 11 years 29 weeks ago. Offline
Joined: 17 Jun 2009
Posts: 23
Hello Eric,
Here is my email adress glenn_dexter@yahoo.com
Thanks for your time.

Glenn
Eric EVRARD
User offline. Last seen 6 years 22 weeks ago. Offline
Joined: 4 Dec 2006
Posts: 25
Groups: None
Hello Glenn,
I don’t know If P6 do this, I guess that you can generate a report with those parameter in the "Reports" features but I am not familiar with it.
Give me your mail adress I will forward you a document relating how I manage to export data in excel to generate Curves and Histograms
Regards
Glenn Dexter Ubaldo
User offline. Last seen 11 years 29 weeks ago. Offline
Joined: 17 Jun 2009
Posts: 23
Dear Eric,

I tried this option and it is shows the over allocated budgedted units in histogram form but is it possible in P6 to generate a report in tabular form showing the average, peak & total budgeted quantity like in P3. i need this values because I am presenting the manpower histogram in excel. your response would be very much appreciated.

Thanks,
Glenn
Eric EVRARD
User offline. Last seen 6 years 22 weeks ago. Offline
Joined: 4 Dec 2006
Posts: 25
Groups: None
Hello,
Go to the "resource usage profile", right click on the histogram and select "Resource Usage Profile Options".
In Additional Data Options, select "Show Limits" and "Show Overallocation", it should works
Regards
Eric
David Kelly
User offline. Last seen 1 year 38 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630
P3 offered "Total, Peak, Average"

P6 just has "total or average"