Hi Joe,



First of all, welcome to Planning Planet!!!



The reason why you get 2019 end date it is because of your resource planned finish date. To resolve your problem try to go to "Assignments’ located at the left corner of your screen and show the start & finish dates.



Now try to trace those 2019 end dates and others then change it the same dates to your activities.



Try this exercise and see what happen.



Hope this helps.



Regards,



Arnold