Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Open End Activity

6 replies [Last post]
Shahzad Ahmad
User offline. Last seen 14 years 39 weeks ago. Offline
Joined: 14 Feb 2008
Posts: 96

Dear All

Problem related to P6

How i can find out open end activity in Log file.

in logic.... it is not clear at all.

Thanks
Shahzad

Replies

Jenn Weber
User offline. Last seen 10 years 35 weeks ago. Offline
Joined: 20 Jan 2011
Posts: 35
Groups: None

You could also try using the logic analyzer in Acumen Fuse to find all open ended activities (as well as leads, lags, out of sequence activities, reverse logic, redundant, and other logic flaws) within your schedule or in multiple linked schedules.  Visit our website for more information or a free trial of the software: http://www.projectacumen.com/fuse/overview/analysis 

Irfan Khan
User offline. Last seen 11 weeks 1 day ago. Offline
Joined: 19 Jul 2009
Posts: 138

hi, 

 

run ur project with data date press F9 Press View Log & under SCHEDLOG.notepad u can see Errors:

Warnings: u can find here (Activities without predecessors) (Activities without successors) (Out-of-sequence activities)

(Activities with Actual Dates > Data Date) (Milestone Activities with invalid relationships) etc.

hope it ill be helpfull....

 

regards,,,,
 

Mangesh Khuspe
User offline. Last seen 27 weeks 5 days ago. Offline
Joined: 10 Apr 2007
Posts: 162

Dear Shahzad,

 

There is also another way for that which Rafael and Gary have suggested and can be found at

http://www.planningplanet.com/forums/primavera-version-pm5-pm6/503663/open-link-activity

 

WIth Regards,

 

Mangesh 

Shahzad Ahmad
User offline. Last seen 14 years 39 weeks ago. Offline
Joined: 14 Feb 2008
Posts: 96
Hi Rob

Thanks for reply i found them.


Thanks
Shahzad
Rob Kane
User offline. Last seen 3 years 25 weeks ago. Offline
Joined: 17 Jan 2004
Posts: 27
Groups: None
If you are looking for open ends, stick in your predecessor &successor columns in a layout and run a filter where they = "null"

Rob
Arnel Lagumbay
User offline. Last seen 11 years 40 weeks ago. Offline
Joined: 31 Aug 2008
Posts: 35
Shahzad

Try to tick the"log to file" when you schedule your

programme,there you can find activities w/o

predecessors&successors.

Hope this help..


Best regards,
arnel