Open End Activity

Member for

14 years 9 months

You could also try using the logic analyzer in Acumen Fuse to find all open ended activities (as well as leads, lags, out of sequence activities, reverse logic, redundant, and other logic flaws) within your schedule or in multiple linked schedules.  Visit our website for more information or a free trial of the software: http://www.projectacumen.com/fuse/overview/analysis 

Member for

16 years 3 months

hi, 

 

run ur project with data date press F9 Press View Log & under SCHEDLOG.notepad u can see Errors:



Warnings: u can find here (Activities without predecessors) (Activities without successors) (Out-of-sequence activities)

(Activities with Actual Dates > Data Date) (Milestone Activities with invalid relationships) etc.

hope it ill be helpfull....

 

regards,,,,

 

Member for

17 years 8 months

Hi Rob



Thanks for reply i found them.





Thanks

Shahzad

Member for

21 years 9 months

If you are looking for open ends, stick in your predecessor &successor columns in a layout and run a filter where they = "null"



Rob

Member for

17 years 2 months

Shahzad



Try to tick the"log to file" when you schedule your



programme,there you can find activities w/o



predecessors&successors.



Hope this help..





Best regards,

arnel