I am trying to import just all the "Resource Names" - I tried many times, but in vain.
I tried searching for YouTube Videos where only "Resource Names" are imported - But could not find a single such video.
I added 2 resources manually in Primavera i.e. NLD-21 & NLD-22 with all details & then exported to Excel with the following fields - Using the Resource Export -
rsrc_short_namersrc_namersrc_typeunit_idrole_iddef_qty_per_hrmax_qty_per_hrResource IDResource Name(*)Resource TypeUnit of Measure(*)Role IDDefault Units / Time(h/d)(*)Max Units/Time(h/d)rsrc_short_namersrc_namersrc_typeunit_idrole_iddef_qty_per_hrmax_qty_per_hrResource IDResource Name(*)Resource TypeUnit of Measure(*)Role IDDefault Units / Time(h/d)(*)Max Units/Time(h/d)NLD-21ParthibanLabor 812NLD-22VijayLabor 812NLD-23VIKASLabor 812NLD-24ANILLabor 812NLD-25SumitLabor 812
Then I opened the Excel file and deleted all other resources which are not part of the current project and added 3 more resources i.e. NLD-23, NLD-24 & NLD-25 with details as specified above.
Then I imported this resource added Excel file in Primavera - But these newely added 3 resources do not get imported even though Primavera displays that the "Import was successful" - I tried atleast 15 different Permutations & Combinations of adding and deleting fields, etc, etc but its not working out. The newely added 3 resources are Not Imported.
Can you tell me why? And what to do?
With Thanks & Best Regards
Member for
16 years 3 months
Member for16 years3 months
Submitted by Zoltan Palffy on Fri, 2021-02-19 14:18
If you are trying to import Resources through the excel import / export in P6 you have to use the Resource Export & not the Resource Assignment option.
The tab named RSRC does allow for the Resource Name to be imported.
Can you please explain how to import the "Resource Names" because the exported excel file has an Asterix (*) in the Resource Name field and is therefore "Un-editable" and ignored by P6 during import.
Member for
8 years
Member for8 years1 month
Submitted by MARIAM SALAMA on Tue, 2018-10-02 04:30
I am receiving the message "Exort failed. Unexpected error from external datadase driver (1). Please contact your administrator to correct the problem.
I am receiving the message "Exort failed. Unexpected error from external datadase driver (1). Please contact your administrator to correct the problem.
There is an option in excel through which you could import csv file, to import csv file first of all open Microsoft Excel and go to Data option, here you will see an option where you can import data from external resource such as txt, xml, form web resources etc. But in case If you want to use any third party software to perform such kinds of action, you should be download MindStick DataConverter. This is very efficient tool through which you can perform many such type of actions and saved file in many extensions, basically it's free charge tool so you have not any difficulty to download it.
I'm posting this question here because I haven't found found option for creating <strong>New Thread, </strong>Actually I have been suffering with one problem since two days I want to import CSV data into excel file and export it in SQL file format, so I want to whether any option or efficient tool to solve this problem. Please resolve my problem as soon as possible or give me any valuable suggestion. </p><p>Thanks in advance!</p>
I'm posting this question here because I haven't found found option for creating New Thread, Actually I have been suffering with one problem since two days I want to import CSV data into excel file and export it in SQL file format, so I want to whether any option or efficient tool to solve this problem. Please resolve my problem as soon as possible or give me any valuable suggestion.
I'm posting this question here becuase I have'nt found found option for creating New Thread, Actually I have been suffering with one problem since two days I want to import CSV data into excel file and export it in sql file format, so I want to whether any option or efficient tool to solve this problem. Please resolve my problem as soon as possibleor give me any valuable suggestion to me.
Sorry for getting back to you late. The problem is that when I choose to export both the activities & relationships. I added to export both predecessor name & the successor activity names. When I open the excel file, I found that I got the first 4 letters of the activity name under these two columns. I did get the complete activity names at the activity name column.
When I export activity ID, Name, and relationships to excel in P6, I got only the frist few letters in the Activity Name column. Anyone can tell me how to modify the length of the exported text in P6?
I knew how to do this in P3.
Member for
19 years 5 months
Member for19 years5 months
Submitted by Izam Zakaria on Mon, 2009-03-23 22:17
First of all, thanks for appreciating my assistance. I am happy to help.
Regarding to your query, to assign resources using excel sheet:
1. Create first the resources in Primavera 6 Windows.
2. After creating, export to excel all the activities don’t have resources assign.
3. make sure that your export type is "Resource Assignment" and include the "Resource ID", Activity ID and Activity Name & Budgeted Units (If necessary).
4. In Resource ID (rsrc_id) column, assign only the unique Resource ID (This is the Resources you newly created in Primavera 6 Windows) to that particular Activity ID & Name and put the units under the “Budgeted Units” column.
Try this and let me know, otherwise I will send you the steps.
Regards,
Arnold
Member for
19 years 5 months
Member for19 years5 months
Submitted by Izam Zakaria on Mon, 2009-03-23 05:39
Its work man. How naive Iam. I thought it was same implemetation with P3. Anyway thank u so much Mr Great Planning Engineer Arnold Puy.You really make my day.
If you will export Resources assigned to your activities, try to use only the the Export Type "Resource Assignments" and include the "Budgeted Units" & Resource ID Name" in your column, just to avoid confusion. Some of the column title having the symbol of (*) cannot be modified in Excel.
Let me know if you did it otherwise, I can send you the steps.
Member for
16 years 3 monthsyou can ammend a column
you can ammend a column
Member for
5 years 8 monthsThanks for your reply Dear
Thanks for your reply Dear Mr. Izam Zakaria.
I am trying to import just all the "Resource Names" - I tried many times, but in vain.
I tried searching for YouTube Videos where only "Resource Names" are imported - But could not find a single such video.
I added 2 resources manually in Primavera i.e. NLD-21 & NLD-22 with all details & then exported to Excel with the following fields - Using the Resource Export -
rsrc_short_namersrc_namersrc_typeunit_idrole_iddef_qty_per_hrmax_qty_per_hrResource IDResource Name(*)Resource TypeUnit of Measure(*)Role IDDefault Units / Time(h/d)(*)Max Units/Time(h/d)rsrc_short_namersrc_namersrc_typeunit_idrole_iddef_qty_per_hrmax_qty_per_hrResource IDResource Name(*)Resource TypeUnit of Measure(*)Role IDDefault Units / Time(h/d)(*)Max Units/Time(h/d)NLD-21ParthibanLabor 812NLD-22VijayLabor 812NLD-23VIKASLabor 812NLD-24ANILLabor 812NLD-25SumitLabor 812
Then I opened the Excel file and deleted all other resources which are not part of the current project and added 3 more resources i.e. NLD-23, NLD-24 & NLD-25 with details as specified above.
Then I imported this resource added Excel file in Primavera - But these newely added 3 resources do not get imported even though Primavera displays that the "Import was successful" - I tried atleast 15 different Permutations & Combinations of adding and deleting fields, etc, etc but its not working out. The newely added 3 resources are Not Imported.
Can you tell me why? And what to do?
With Thanks & Best Regards
Member for
16 years 3 monthscheck your filters for the
check your filters for the missing activities
for cost issue make sure that calculate cost from units is set to no for ALL activities.
Member for
8 years 1 monthIf you are trying to import
If you are trying to import Resources through the excel import / export in P6 you have to use the Resource Export & not the Resource Assignment option.
The tab named RSRC does allow for the Resource Name to be imported.
Regards,
Steven
Member for
5 years 8 monthsCan you please explain how
Member for
8 yearsHello for all I have problem
Hello for all
I have problem when i expert exel sheet with activity name and id it comming sheet empty in task no id .no actovity name .idonot know why ?
Member for
8 years 1 monthKeith,As Zoltan stated
Keith,
As Zoltan stated earlier, there appears to be a bug in some of the Microsoft updates installed on the 10th October.
These contained updates to the Microsoft Jet Database Engine & it appears to be causing Database issues with Microsoft Access as well.
There appears to be a couple of Microsoft updates that may be causing the issue depending on Windows Version.
See link below for possible solutions:
https://social.technet.microsoft.com/Forums/en-US/45ebe780-967e-4748-a146-9ec7a15626dc/unexpected-error-from-external-database-driver-1?forum=itmanagerOn
Please note that this bug has been reported to Oracle (Last Update 6th November):
https://support.oracle.com/knowledge/More%20Applications%20and%20Technologies/2317408_1.htmlHope this helps.
Steven
Member for
7 years 11 monthsHello Everyone,I am receiving
Hello Everyone,
I am receiving the message "Exort failed. Unexpected error from external datadase driver (1). Please contact your administrator to correct the problem.
Any input/ help is more than appreciated.
Keith
Member for
7 years 11 monthsHello Everyone,I am receiving
Hello Everyone,
I am receiving the message "Exort failed. Unexpected error from external datadase driver (1). Please contact your administrator to correct the problem.
Any input/ help is more than appreciated.
Keith
Member for
7 years 11 monthsHello Ali, I am experiencing
Hello Ali,
I am experiencing the same problem and was wondering if you ever received a solution?
Thanks
Member for
16 years 3 monthsthere is also a bug what
there is also a bug what version are you using ?
Member for
8 years 7 monthsDear Zolfan, Thank you for
Dear Zolfan,
Thank you for your reply.
This problem was from first and it is not new.
We were not able export to excel. I dont know it is microsoft problem or P6 admin access problem.
Member for
16 years 3 monthsALi if this problem jsut
ALi
if this problem jsut recently happend it is do to an udate from Microsoft foe excel. Roll back the microsoft update and it wil work again
Member for
8 years 7 monthsHi everybody, Please help me
Hi everybody,
Please help me to solve my problem.
I cannot export schedule from P6 to excel. The below error message is coming:
"Export failed. Unexpected error from external database driver (1) please contact your administrator to correct the problem."
Please advice me how to solve this problem.
Member for
8 years 7 monthsHi everybody, Please help me
Hi everybody,
Please help me to solve my problem.
I cannot export schedule from P6 to excel. The below error message is coming:
"Export failed. Unexpected error from external database driver (1) please contact your administrator to correct the problem."
Please advice me how to solve this problem.
Member for
14 years 2 monthsWell, this might be a bit
Well, this might be a bit late, but for others who might be struggling with importing updates from excel, I've put together a step by step video tutorial with a real-world project example. If you're interested, have a look https://www.planacademy.com/excellerate-your-updates-how-to-import-your-subcontractors-primavera-updates-from-excel/
Also, on re-importing data, all excell data must be of "TEXT" type for the reimport to work. It's all outlined in the post.
Regards,
Michael
Member for
13 years 8 monthsHi Ankit Singh,There is an
Hi Ankit Singh,
There is an option in excel through which you could import csv file, to import csv file first of all open Microsoft Excel and go to Data option, here you will see an option where you can import data from external resource such as txt, xml, form web resources etc. But in case If you want to use any third party software to perform such kinds of action, you should be download MindStick DataConverter. This is very efficient tool through which you can perform many such type of actions and saved file in many extensions, basically it's free charge tool so you have not any difficulty to download it.
MindStick DataConverter Download Link: http://mindstick.com/Product/ProductDC.aspx
I hope it might be useful for you.
Member for
13 years 8 monthsHello Everyone, I'm posting
Hello Everyone,
I'm posting this question here because I haven't found found option for creating <strong>New Thread, </strong>Actually I have been suffering with one problem since two days I want to import CSV data into excel file and export it in SQL file format, so I want to whether any option or efficient tool to solve this problem. Please resolve my problem as soon as possible or give me any valuable suggestion. </p><p>Thanks in advance!</p>
Member for
13 years 8 monthsHello Everyone,I'm posting
Hello Everyone,
I'm posting this question here because I haven't found found option for creating New Thread, Actually I have been suffering with one problem since two days I want to import CSV data into excel file and export it in SQL file format, so I want to whether any option or efficient tool to solve this problem. Please resolve my problem as soon as possible or give me any valuable suggestion.
Thanks in advance!
Member for
13 years 8 monthsHello Everyone,I'm posting
Hello Everyone,
I'm posting this question here becuase I have'nt found found option for creating New Thread, Actually I have been suffering with one problem since two days I want to import CSV data into excel file and export it in sql file format, so I want to whether any option or efficient tool to solve this problem. Please resolve my problem as soon as possibleor give me any valuable suggestion to me.
Thanks in advance!
Member for
18 years 6 monthsRE: Excel Import/Export Resource data problem P6
Hi Kevin,
Just now, I did the exercise but its works fine. I think you can send me your .xer file @ primavera6@live.com and I will try to fix it.
Anyway, how did you export your data to excel? I think you miss something.
Regards,
Arnold
Member for
20 years 3 monthsRE: Excel Import/Export Resource data problem P6
Arnold,
Sorry for getting back to you late. The problem is that when I choose to export both the activities & relationships. I added to export both predecessor name & the successor activity names. When I open the excel file, I found that I got the first 4 letters of the activity name under these two columns. I did get the complete activity names at the activity name column.
Member for
18 years 6 monthsRE: Excel Import/Export Resource data problem P6
Hi Kevin,
First of all, WELCOME to Planning Planet.
I tried to export the Activity name but I got a complete name and text similar to the P6.
Can you explain a little bit in detail.
Regards,
Arnold
Member for
20 years 3 monthsRE: Excel Import/Export Resource data problem P6
When I export activity ID, Name, and relationships to excel in P6, I got only the frist few letters in the Activity Name column. Anyone can tell me how to modify the length of the exported text in P6?
I knew how to do this in P3.
Member for
19 years 5 monthsRE: Excel Import/Export Resource data problem P6
A big thanks to you. Its really useful
Member for
18 years 6 monthsRE: Excel Import/Export Resource data problem P6
Hi Izam,
First of all, thanks for appreciating my assistance. I am happy to help.
Regarding to your query, to assign resources using excel sheet:
1. Create first the resources in Primavera 6 Windows.
2. After creating, export to excel all the activities don’t have resources assign.
3. make sure that your export type is "Resource Assignment" and include the "Resource ID", Activity ID and Activity Name & Budgeted Units (If necessary).
4. In Resource ID (rsrc_id) column, assign only the unique Resource ID (This is the Resources you newly created in Primavera 6 Windows) to that particular Activity ID & Name and put the units under the “Budgeted Units” column.
Try this and let me know, otherwise I will send you the steps.
Regards,
Arnold
Member for
19 years 5 monthsRE: Excel Import/Export Resource data problem P6
But Arnold,
What about if the activites have no resource name and ID which I want to assign the resource via excel? Sorry again I need your help.
Member for
19 years 5 monthsRE: Excel Import/Export Resource data problem P6
Its work man. How naive Iam. I thought it was same implemetation with P3. Anyway thank u so much Mr Great Planning Engineer Arnold Puy.You really make my day.
Member for
18 years 6 monthsRE: Excel Import/Export Resource data problem P6
Hi Izam,
If you will export Resources assigned to your activities, try to use only the the Export Type "Resource Assignments" and include the "Budgeted Units" & Resource ID Name" in your column, just to avoid confusion. Some of the column title having the symbol of (*) cannot be modified in Excel.
Let me know if you did it otherwise, I can send you the steps.
Regards,
Arnold