How to Upgrade P5 to P6 - Urgent!!

Member for

16 years 9 months

Thanks Guys,



I already fixed it, i didn’t notice that my P6 has different portfolio and resources filter, that’s why the formatting will not match..I get the information from another discussion here in PM5/PM6 Resources and Global Change in P6...

Tnx a lot,

Member for

19 years 11 months

Joseph,



Your P5 files are intack as long as those converted to P6 have different directories/folders.

Member for

18 years 9 months

Joseph



On the cds of P6 there is a script to upgrade the database. You can find there a readme file as well. No need to upgrade project by project.



Good luck!

Dieter

Member for

16 years 9 months

Yes Jaime that’s what i mean, because we are trying to transfer all the datas from P5 to P6. As you mentioned that the individual projects may changed, is the default resources from P5 may changed as well? Because what we want is to maintain all the files from P5 including projects, resources, formating, and etc...so that when we have another project its easy f0r us to assign resources using the default from P5..

Member for

19 years 11 months

You have mentioned configuration, does this means database configuration? If your importing P5 files for P6, see that there is a box to modify ( keep existing, updates, replace) globally you cannot change, but individual projects can be changed. Good Luck