Show Progress Line?

3 replies [Last post]
Johnny Wee
User offline. Last seen 6 years 34 weeks ago. Offline
Joined: 23 Jul 2007
Posts: 21
Groups: GPC Qatar
How to show Progress Line in P6?

Replies

Dieter Wambach
User offline. Last seen 7 years 1 week ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Peter

You can show the progress as bars - as you said.
My impression was that he was missing the progress line of P3.

Regards
Dieter
Peter Nicol
User offline. Last seen 13 years 51 weeks ago. Offline
Joined: 31 Jan 2009
Posts: 23
Groups: None
Dieter, actually doesn’t the Percentage complete option for bars show the progress on the bar chart ?

I think that is he is after

- Peter.
Dieter Wambach
User offline. Last seen 7 years 1 week ago. Offline
Joined: 15 Jan 2007
Posts: 1350
In P6 there is no progress line. You can show some varances (group by, filter, display within the table) and of course BL-bar vs. actual bar.