Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Importing files from p3 to p3e

2 replies [Last post]
Stanley Obeleagu
User offline. Last seen 14 years 20 weeks ago. Offline
Joined: 6 Feb 2009
Posts: 6
I recently imported a work program from p3 to p3e and

noticed that some key dates(M.C.,Ready for

commissioning,Demobilisation) changed when i rescheduled

the P.O.W.(Programme Of Work) What could be the problem?

Replies

Stanley Obeleagu
User offline. Last seen 14 years 20 weeks ago. Offline
Joined: 6 Feb 2009
Posts: 6
Thank you Dieter,

I will check it out.

Regards,

Stanley.
Dieter Wambach
User offline. Last seen 7 years 1 week ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Stanley

On your documentation cd there is a directory From P3 to P6: Before you’ll start the import read this chapter: "Converting P3 Projects to P6" (starts page 115) to understand the differences.
In your case I assume most probably reasons are the calendars or the scheduling options (lags?).

Good luck
Dieter