"Timesheets and baselines are not exported when you export project data. With the appropriate access, you can export secure codes and secure code assignments to XML format; however, you cannot export them to XER format. For more information about secure codes, refer to Primavera’s Administrator’s Guide."
Member for
19 yearsRE: P6.1 Exporting baselines
I have just had an e mail from my client suggesting just that.
Thanks for your reply
Roger
Member for
22 years 7 monthsRE: P6.1 Exporting baselines
Of course you can allways recover the baseline as a project and send it to your client as a XER.
HTH
Member for
19 yearsRE: P6.1 Exporting baselines
Seek and ye shall find
Found this in the PM handbook
"Timesheets and baselines are not exported when you export project data. With the appropriate access, you can export secure codes and secure code assignments to XML format; however, you cannot export them to XER format. For more information about secure codes, refer to Primavera’s Administrator’s Guide."
Thanks anyway
Roger