P6.1 Exporting baselines

Member for

19 years

I have just had an e mail from my client suggesting just that.

Thanks for your reply



Roger

Member for

22 years 7 months

Of course you can allways recover the baseline as a project and send it to your client as a XER.



HTH

Member for

19 years

Seek and ye shall find



Found this in the PM handbook



"Timesheets and baselines are not exported when you export project data. With the appropriate access, you can export secure codes and secure code assignments to XML format; however, you cannot export them to XER format. For more information about secure codes, refer to Primavera’s Administrator’s Guide."



Thanks anyway



Roger