I want this functionality in the resource assignments view, not the activity view. Currently I have to either create a filter or run a global change as described earlier
You can view your activity status even without viewing the resource assignments. In Activity Window, you can display Activity Status in your column for each activity, Not Started, In Progress & Completed. Is this what you mean?
RE: Activity Status in the Resource Assignments View
Thanks Dang..I will try..
Regards
RE: Activity Status in the Resource Assignments View
Hi L. Dang,
Great!! How did you paste the image/picture?
Regards,
Arnold
RE: Activity Status in the Resource Assignments View
Hi Mark,
YES, I think this is the only way we can do.
Arnold
RE: Activity Status in the Resource Assignments View
Hi Arnold,
I want this functionality in the resource assignments view, not the activity view. Currently I have to either create a filter or run a global change as described earlier
Cheers
Mark
RE: Activity Status in the Resource Assignments View
Hi Mark,
You can view your activity status even without viewing the resource assignments. In Activity Window, you can display Activity Status in your column for each activity, Not Started, In Progress & Completed. Is this what you mean?
Arnold