The Start date and finish date is not matching according to the duration given. calendar assigned is same for all activities. Can anyone tell me the reason for this wrong dates.
Member for
17 years 3 months
Member for17 years3 months
Submitted by Abeer Mahmoud on Wed, 2008-09-10 05:09
Member for
9 years 2 monthsDear Allhow we can insert new
Dear All
how we can insert new project with different calendar in existing project in primavera?
Sincerely Yours
H.Najmzadeh
Member for
9 years 7 monthsHi everyone,
Hi everyone,
The Start date and finish date is not matching according to the duration given. calendar assigned is same for all activities. Can anyone tell me the reason for this wrong dates.
Member for
17 years 3 monthsRE: assign calendars to many activities in one step
Thanks for all of you it works.
Abeer Mohamed Taher
Member for
17 years 3 monthsRE: assign calendars to many activities in one step
Hi Abeer,
To add a calender in one step, try this:
1- Add calender Column from Column (General Option.
2-Add desired Calender to First activity on Top of the Column.
3- Point the arrow on empty Calender Cell at the Bottom of the Calender Column.
4- By using(SHIFT + UP ARROW) OR (SHIFT + MOUSE POINTER) highlight the activities From bottom to Top......upto the assigned calender.
5- As you Reach the Assigned Calendr, make Right click choose Fill Down.
you can use same way to add any item.
best regard
riad
Member for
18 years 6 monthsRE: assign calendars to many activities in one step
Hi Abeer,
You can assign calendar for the existing activities using GLOBAL CHANGE.
Calendar = "Select Calendar"
If you wanted to change the selected activities only then you need to filter prior to run Global change.
Arnold
Member for
20 years 3 monthsRE: assign calendars to many activities in one step
Did you try Edit->Fill Down (CTRL+E)?