If you want that your Actual Units will remain zero during progress, you must have to go to Project, select your current project. In Project Detail Tab select Calculations and uncheck “Recalculate Actual Units and Cost when duration % complete changes”.
Activity Type = Task Dependent and Duration Type must be equal to “Fixed Duration & Units”. However, if your Duration Type = Fixed Duration and Units/Time, during progress the Actual Units = 0 and “At Completion Units” is equal to “Remaining Units” and is not equal to “Budgeted Units”.
Member for
18 years 6 monthsRE: Scheduling without actual units
Hi,
If you want that your Actual Units will remain zero during progress, you must have to go to Project, select your current project. In Project Detail Tab select Calculations and uncheck “Recalculate Actual Units and Cost when duration % complete changes”.
Activity Type = Task Dependent and Duration Type must be equal to “Fixed Duration & Units”. However, if your Duration Type = Fixed Duration and Units/Time, during progress the Actual Units = 0 and “At Completion Units” is equal to “Remaining Units” and is not equal to “Budgeted Units”.
Arnold
Member for
17 years 4 monthsRE: Scheduling without actual units
I think the most of problem is when we fixed the durations and unit/times,the autual units will go with the %comp