Activities Pasted in Reverse Order

1 reply [Last post]
Johnny Xu
User offline. Last seen 5 years 6 weeks ago. Offline
Joined: 24 Apr 2002
Posts: 12
Hi,

When I copy a group of activities and paste them, say at the next of the original, the pasted activities appear in reverse order. Any solution? Thanks.

Johnny

Replies

Alex Wong
User offline. Last seen 11 years 4 weeks ago. Offline
Joined: 12 Feb 2003
Posts: 874
Groups: TILOS
Johnny

You adjust the organise and sort by start dates and then finish date will fix this problem

And these date we are not too worry about the activity number anymore, simply because we do not need to use an intelligent numbering system since we have unlimited number of codes and UDF. Activity ID become just a number so we can use other information to group and sort and ordering.

HTH