It happens when you have a finish milestone with a FS relationship to another finish milestone. This should be a FF relationship. Its a similar fix with start milestones etc.

Member for

19 years 1 month

it depends if it is a start milestone or a finish milestone, you have to assign corresponding relationship for start and or finish, ask yourself if it is valid to assign a FF for a start milestone?

Member for

17 years 6 months

If you have FS relationships with in the mile stones this is displayed as invalid relation ship in schedule log/report.



This is one of the cases.

Member for

18 years 9 months

Ladi

Don’t worry! For milestones not all relationships are available. If an activity had a different type before you may have assigned an not allowad relation. For scheduling start or finish of a milestone is the same. Until now I never found a susequent error to this one. Just ignore it.

Regards

Dieter