It happens when you have a finish milestone with a FS relationship to another finish milestone. This should be a FF relationship. Its a similar fix with start milestones etc.
it depends if it is a start milestone or a finish milestone, you have to assign corresponding relationship for start and or finish, ask yourself if it is valid to assign a FF for a start milestone?
Member for
17 years 6 months
Member for17 years6 months
Submitted by Satya Narayana on Thu, 2008-05-22 02:28
Dont worry! For milestones not all relationships are available. If an activity had a different type before you may have assigned an not allowad relation. For scheduling start or finish of a milestone is the same. Until now I never found a susequent error to this one. Just ignore it.
Member for
17 years 6 monthsRE: Milestone Activities with invalid relationships?
It happens when you have a finish milestone with a FS relationship to another finish milestone. This should be a FF relationship. Its a similar fix with start milestones etc.
Member for
19 years 1 monthRE: Milestone Activities with invalid relationships?
it depends if it is a start milestone or a finish milestone, you have to assign corresponding relationship for start and or finish, ask yourself if it is valid to assign a FF for a start milestone?
Member for
17 years 6 monthsRE: Milestone Activities with invalid relationships?
If you have FS relationships with in the mile stones this is displayed as invalid relation ship in schedule log/report.
This is one of the cases.
Member for
18 years 9 monthsRE: Milestone Activities with invalid relationships?
Ladi
Dont worry! For milestones not all relationships are available. If an activity had a different type before you may have assigned an not allowad relation. For scheduling start or finish of a milestone is the same. Until now I never found a susequent error to this one. Just ignore it.
Regards
Dieter