Hi Alex
Sorry I was not feeling well and had a surgery therefore I didnt check my emails. Right now everything is fine.
Yes I can send you print print screen but I need your email address . I dont know any attachment option in this forum.
Thanks
Minhas
Minhas
If you open the resource tab in the view "activities"; is this ok?
- Sorry, what do you exactly mean by "resources spread sheet"? Is it the "resource usage spreadsheet"?
- Is there a filter in the resource usage spreadsheet?
- View Projects --> tab "resources" --> "Drive activity dates by default" is it marked? Per activity you can access this parameter as well per activity: right mouse button --> columns --> category "general" --> ...
Hope this helps
Dieter
Thanks Alex
I have tried everything but still not working. I reinstalled my Primavera software. and tried to assign new budgeted hours but still same problem.
I am getting budgeted hours in columns correctly but not in resources spread sheet.
Does anybody solve my problem.
Please advise.
1. Resource assignments - Plan units does it add up to Activity level
2. Resource Assignment - Plan Start same as activity level
3. Plan Cureve is base on correct baseline schedule
4. You select the right preference in the summaried data, Time scale = Week or day or month, that will affect it on the tracking view but it will be ok if you open the project and display it live
RE: Budgeted & Actual Units Issue in Spread Sheet
Hi Minhas
Can you have a look at your BL and Plan start and finish date.
It seem that then might not be align with your actual dates
HTH
Alex
RE: Budgeted & Actual Units Issue in Spread Sheet
Hi Alex
Sorry I was not feeling well and had a surgery therefore I didnt check my emails. Right now everything is fine.
Yes I can send you print print screen but I need your email address . I dont know any attachment option in this forum.
Thanks
Minhas
RE: Budgeted & Actual Units Issue in Spread Sheet
Minhas
Can you post a screen shot, I believe we can help you but you have to give a bit more information
Alex
RE: Budgeted & Actual Units Issue in Spread Sheet
are you using resource(s) calendar(s)? i supposed differences between activity calendars and resource calendars create the problem
RE: Budgeted & Actual Units Issue in Spread Sheet
Minhas
If you open the resource tab in the view "activities"; is this ok?
- Sorry, what do you exactly mean by "resources spread sheet"? Is it the "resource usage spreadsheet"?
- Is there a filter in the resource usage spreadsheet?
- View Projects --> tab "resources" --> "Drive activity dates by default" is it marked? Per activity you can access this parameter as well per activity: right mouse button --> columns --> category "general" --> ...
Hope this helps
Dieter
RE: Budgeted & Actual Units Issue in Spread Sheet
Thanks Alex
I have tried everything but still not working. I reinstalled my Primavera software. and tried to assign new budgeted hours but still same problem.
I am getting budgeted hours in columns correctly but not in resources spread sheet.
Does anybody solve my problem.
Please advise.
Regards,
Minhas
RE: Budgeted & Actual Units Issue in Spread Sheet
Couple things you need to check
1. Resource assignments - Plan units does it add up to Activity level
2. Resource Assignment - Plan Start same as activity level
3. Plan Cureve is base on correct baseline schedule
4. You select the right preference in the summaried data, Time scale = Week or day or month, that will affect it on the tracking view but it will be ok if you open the project and display it live
HTH
Alex