Oracle Primavera - PM6 Member for 18 years 1 month Member for 18 years 1 month Submitted by K D on Mon, 2008-05-05 05:06 Permalink RE: Estimate to Complete Calculation Hi. If Im not wrong there is only 1 CPI. CPI = Earned value / Actual cost. Log in or register to post comments
Member for 18 years 1 month Member for 18 years 1 month Submitted by K D on Mon, 2008-05-05 05:06 Permalink RE: Estimate to Complete Calculation Hi. If Im not wrong there is only 1 CPI. CPI = Earned value / Actual cost.
Member for
18 years 1 monthRE: Estimate to Complete Calculation
Hi.
If Im not wrong there is only 1 CPI.
CPI = Earned value / Actual cost.