The duration shown in a WBS activity is based on the WBS activitys calendar. When you press F9, the WBS duration is back-calculated based on its start and finish dates on the calendar you have chosen.
***** NOTE ******
The duration of a level-of-effort activity is based on the Early dates of the hammocked activities, a WBS summary is based on Planned dates BE CAREFULL!!
Member for
18 years 9 months
Member for18 years9 months
Submitted by Dieter Wambach on Mon, 2008-03-31 18:11
Member for
21 yearsRE: WBS level duration in PM5/6
The duration shown in a WBS activity is based on the WBS activitys calendar. When you press F9, the WBS duration is back-calculated based on its start and finish dates on the calendar you have chosen.
***** NOTE ******
The duration of a level-of-effort activity is based on the Early dates of the hammocked activities, a WBS summary is based on Planned dates BE CAREFULL!!
Member for
18 years 9 monthsRE: WBS level duration in PM5/6
Salut Alexandre
For the summary bars always the default calendar is used.
There are already some threads on this item. Have a look at
http://www.planningplanet.com/forum/forum_post.asp?fid=1&Cat=8&Top=43946
Regards
Dieter