Hi Tobi,

In p3e the S Curve is less pain ..

Its very simple you no need to export the data and all ..

Go to activity Usage profile (click on acitivity usage profile and in the bottom section click on all activities and in the graph area right click and click on acitivity usage profile option remove all checks from Bydate and click on cumulative checks against baseline, actual and remaining.



Good luck