Updating activity dates, %complete

Member for

18 years 5 months

Johny is right, regarding Schedule Update.

I would add, that the Activity % complete (technical progress) will depend on the EVT you choose in WBS view.



Regards.




Member for

18 years 1 month

Your question is not very clear! What do you mean by “I am trying to change my activity dates ..” Are you doing an update? If this is the case you have to check :

•The actual start

•The actual finish

•The remaining duration for activities started and not finished

•The data date

•The schedule function (F9)



Regards