Incorrect Durations Showing

Member for

18 years 11 months

Thanks a lot folks.



It was that simple. The default calendar was incorrect for the schedule.



Cheers,



Matt

Member for

21 years 6 months

Hi Matt,

Be sure that the default calender is the same project calender. Primavera use the default calender in rolling up the duration information regard less the project calender.

Hope this help,

Taher

Member for

19 years

Hi Matt,



Check your Hours per Time Period setting. Make sure it match to your calendar settings. Durations are calculated from the Hours per Time Period which can be set on Admin preference or User preference under Time Units Tab if “Allow users to specify the number of hours for each time period” is tick.



Hope this help,

Rodel