Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

P5 planned value labour units & earned value labour uni

1 reply [Last post]
Donovan Govender
User offline. Last seen 6 years 24 weeks ago. Offline
Joined: 1 Dec 2005
Posts: 20
Groups: None
I need to show a histogram with planned, actual & earned and scurves for the same in one profile,
my profile histogram shows my budget,baseline,and actual,but the scurves,I have the planned value labour units & earned value labour units ticked but is not showing,

Please help

Regards
Donovan

Replies

Rodel Marasigan
User offline. Last seen 1 year 16 weeks ago. Offline
Joined: 25 Oct 2006
Posts: 1516
Donovan,

Is your schedule resource? If not? then not possible. If resource then have you tick the cummulative or just By Date?

HTH