SPLITTING PROJECTS

Member for

20 years 8 months

Mangesh,



Direct copying or cut & paste of activities is not simple but there is an easy way around.



Open both projects open. Do not group the project by anything - this way activities of both projects will be listed together. Add a column for WBS. Now if you want to take an activity from prject A to B, just change its WBS. Simple like that.

Member for

21 years 2 months

Hi fellow planners,



many thanks for your responses, I have not had any time to try to implement your suggestion. I will "experiment" them on a local copy, before affecting the "live" file.



Thanks agains.



Seb

Member for

19 years

Mangesh,



You can copy and paste using WBS into different Projects under WBS module in P5. Much easier.



HTH

Member for

18 years 6 months

Hi all



if you are using P5 then its not so simple coz copying of activities option does not work in two different projects.

you have to use methodology management module.

tell me if i am wrong.

the approach of thomas is very gud.





cheers



Mangesh

Member for

23 years 8 months

create the new projects, then open the original project and new created projects at the same time, cut the activities from original and paste into new project.



No lose in information EXCEPT you have different structures.

Member for

19 years

Hi,



You can drag and drop, Copy & Paste or Cut and Paste without losing link which will prompt you what information you would like to carried when moving or coping WBS to another project under WBS module.

Member for

24 years 5 months

Sebastian:



I had the same problem as you recently, when developing a 230,000 activity schedule.

I decided to split the project into 11 other subprojects.

The way I did it was using the WBS. First I created the new projects and then I copied sections of the parent project WBS into each of the child projects. This copied all the activities within the WBS sections. I kept the original project as backup

In my case it was easy regarding the relationships between projects because there were very few between them. I assigned those relationships after the splitting so I am not sure whether they can stay if you split afterwards.



I hope this helps.



Tomas Rivera