Its just an idea (I have only P5 and P6 availabel):
New Report --> Group "Activities" --> Add sub area "Activity Steps" --> add required data items + some in reserve (to replace them using the editor with items you need but cant achieve with the wizzard) --> filter by wbs.
Hope this will help.
Dieter
I do not play with Primavera at home, so its difficult at the moment to test. But one idea come to my mind. If it is not possible to filter on WBS, you could create a new project in a Simulation Space , that contains the particular WBS you want.
What do you think about it ?
Kindest regards.
Patricia
RE: ACTIVITY STEPS REPORT FOR FEW WBS
Hi Suresh
Its just an idea (I have only P5 and P6 availabel):
New Report --> Group "Activities" --> Add sub area "Activity Steps" --> add required data items + some in reserve (to replace them using the editor with items you need but cant achieve with the wizzard) --> filter by wbs.
Hope this will help.
Dieter
RE: ACTIVITY STEPS REPORT FOR FEW WBS
Hello Suresh,
I do not play with Primavera at home, so its difficult at the moment to test. But one idea come to my mind. If it is not possible to filter on WBS, you could create a new project in a Simulation Space , that contains the particular WBS you want.
What do you think about it ?
Kindest regards.
Patricia