Hi Sada



It depends from what you intend to do.



- Monthly budget: keep them in EXCEL, run a P3e-report for budgeted and actual costs into Excel, then compare.

- To get actual against planned figures: For my experience this in general was the solution. Create a time-distributed report to compare baseline and actual.

In Germany Spending Plan is very seldom used. I’m very interested to learn a better solution.



Regards

Dieter

Member for

19 years 1 month

Thanks..Dieter Wambach



Is there any alternate solution for this issue for long term projects.



Sada

Member for

18 years 9 months

Hi



Yes, it’s limited to 48 months.