- Monthly budget: keep them in EXCEL, run a P3e-report for budgeted and actual costs into Excel, then compare.
- To get actual against planned figures: For my experience this in general was the solution. Create a time-distributed report to compare baseline and actual.
In Germany Spending Plan is very seldom used. Im very interested to learn a better solution.
Regards
Dieter
Member for
19 years 1 month
Member for19 years1 month
Submitted by sadasivan vish… on Mon, 2007-08-27 09:12
Member for
18 years 9 monthsRE: Primavera 5 spending plan
Hi Sada
It depends from what you intend to do.
- Monthly budget: keep them in EXCEL, run a P3e-report for budgeted and actual costs into Excel, then compare.
- To get actual against planned figures: For my experience this in general was the solution. Create a time-distributed report to compare baseline and actual.
In Germany Spending Plan is very seldom used. Im very interested to learn a better solution.
Regards
Dieter
Member for
19 years 1 monthRE: Primavera 5 spending plan
Thanks..Dieter Wambach
Is there any alternate solution for this issue for long term projects.
Sada
Member for
18 years 9 monthsRE: Primavera 5 spending plan
Hi
Yes, its limited to 48 months.
Dieter