Primavera 5 spending plan

3 replies [Last post]
sadasivan vishnud...
User offline. Last seen 4 years 51 weeks ago. Offline
Joined: 9 Sep 2006
Posts: 5
Groups: None
Hi all,

Is there any limitations for spending plan column in P5.

I’m facing some problems while adding spending plans in EPS level..there i can only fill maximum of 48 months plan..
Pls advise.

Replies

sadasivan vishnud...
User offline. Last seen 4 years 51 weeks ago. Offline
Joined: 9 Sep 2006
Posts: 5
Groups: None
Thanks..Dieter Wambach

Is there any alternate solution for this issue for long term projects.

Sada
Dieter Wambach
User offline. Last seen 7 years 1 week ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Hi

Yes, it’s limited to 48 months.

Dieter
Dieter Wambach
User offline. Last seen 7 years 1 week ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Hi Sada

It depends from what you intend to do.

- Monthly budget: keep them in EXCEL, run a P3e-report for budgeted and actual costs into Excel, then compare.
- To get actual against planned figures: For my experience this in general was the solution. Create a time-distributed report to compare baseline and actual.
In Germany Spending Plan is very seldom used. I’m very interested to learn a better solution.

Regards