Migrating From P3e V 4.1 to V 5.0 (Baseline )

Member for

18 years 9 months

Salut Patricia



There are two ways:

1. The normal way to start a SQL-Skript on the CD to transform the database from 4.1 to 5. Later the user will just realize some different screens and functions. Most IT departments inform the users. Baselines are still connected.

2. Single projects to be transferred e.g. from a backup database. Then it will be the complicate way as described by Niek - unlink --> export projects + BL --> import --> link again.



Regards and a have a nice Sunday



Dieter

Member for

18 years 5 months

William,



I am just a user, and do not know all "secrets" of migration. But I am a little bit surprised of this problem. I am quite sure there is a way, that doesn’t need to unlink baselines. I nether heard of this problem (and projects I am working for had also migrated from V4 to V5 with their baselines). I hope someone else has the answer.



Best regards.

Patricia

Member for

20 years 7 months

I’m afraid you can’t William.



You should unlink the baseline in the 4.1 schedule and import these separately.



H.T.H.