Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

P3e - Local Copy running through MS-SQL Server

No replies
Matt Rudge
User offline. Last seen 15 years 45 weeks ago. Offline
Joined: 12 Mar 2007
Posts: 29
Groups: None
Hi all,

I currently run P5 through an MS-SQL server locally while we finalise our central database structure and will keep the local copy to enable remote working.

The only thing is there is currently no replica or back-up set up from the server and I have asked our IT dept and they are not sure how to do this!

Does anyone else run P5 through MS-SQL with a back-up function? If so can you please let me know how this was setup??

Thanks,

Matt