Minhas Shaikh
User offline. Last seen 13 years 9 weeks ago. Offline
Joined: 30 Mar 2007
Posts: 44
Hi Planners,
I have a problem for resource useage profile.

After assigning resource budgeted and actual units . In resource usage profile graph, it shows budgeted , remaining unit curves only not "actual units curve". if we double click on graph it will give all values of budgeted, remaining as well as actuals .
I also click on "resource usage profile options" and all are allowed to show.

Can anybody help me solve this problem.

Minhas

Replies

Minhas Shaikh
User offline. Last seen 13 years 9 weeks ago. Offline
Joined: 30 Mar 2007
Posts: 44
Thanks for everybody.. I solved my problem.
Patricia Le Clainche
User offline. Last seen 9 years 24 weeks ago. Offline
Joined: 18 May 2007
Posts: 86
Groups: None
Minhas,

Do you systematically have the pb or is it from tile to time ?

I met some problems like your in Resources Profile Graph in Activities View. I think it was due to a wrong choice of StartUp Filters (in User Preferences).

Maybe someone else met such troubles ?
Rodel Marasigan
User offline. Last seen 1 day 28 min ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Minhas,

Right click your graph area and select Profile Settings then tick the actual cumulative tick box. That should show your actual curves.

HTH